Projects, Studies and Programs: Freight Railroad Relocation Project - Santa Clara Valley Transportation Authority
skip to main content skip to related links skip to website navigation links
VTA Home
Customer Service Phone: (408) 321-2300


   Related Links


   2000 Measure A

       Ballot
       Ballot Specified Projects
       Citizen Watchdog Committee
       Revenue & Expenditure Plan

   Planning/Studies

   Construction

       Current Projects
       Completed Projects

   Programs



Freight Railroad Relocation Project

Project Overview and History

The Freight Railroad Relocation (FRR) Project spans approximately eight miles of railroad beginning in Fremont at Grimmer Boulevard passing through Milpitas and ending at Montague Expressway in San Jose. The Santa Clara Valley Transportation Authority (VTA) acquired the right-of-way in December 2002 from the Union Pacific Railroad (UPRR) securing a vital north/south transit corridor for Santa Clara County.

Project Objective

Several maintenance activities are necessary to transform this very important corridor and make space for future transit. These important works activities include relocating UPRR freight tracks, relocating utilities, grade separating several major intersections, and enhancing flood control measures at multiple creeks.

Upcoming Summer 2008 Work

VTA will begin relocating utilities to lower depths using Horizontal Directional Drilling technology at eight site total throughout the FRR alignment.

Time: Monday - Saturday, 7 a.m. - 7 p.m.
Locations: Three sites at any one time.
Durations: Approximately three weeks at each site.

Phase 1: Mobilization (3-5 days)
Activity: Crews will begin to assemble materials and set up equipment on site.
Impact: Minor noise from diesel engines. Minor traffic impacts with brief lane closures. Dust will be controlled.

Phase 2: Drilling Operations (5-12 days)
Activity: Drilling will concentrate around the entry pit location, while welding and pip assembly will occur near the exit pit and extend along the corridor.
Impact: Expect constant diesel engine noise from drill rig, excavators and consturction. No banging or pile-driving noise. Drill rigs may be visible over adjacent sound walls.

Phase 3: Pipe Installation and De-Mobilization (3-5 days)
Activity: A long welded pipe will be pulled through the single bore path at each location. Drill rigs will be dismantled and moved to another location.
Impact: Minor noise from diesel engines. Dust will be controlled.

Horizontal Directional Drilling:

VTA will implement horizontal directional boring technology to install relocated utilities at select road intersections and creek crossings. Directional drilling is a proven technology that creates less traffic congestion, saves time, and is safer for the environment because it does not disturb the above ground surface. Traditional trenching methods are more disruptive to the public and will be used sparingly.

Image shows how a drill rig will start at an entry pit and bore under each roadway or creek at an angle and come up on the other side at an exit pit. Traffic will not be disrupted. 

Project Schedule

  • Utility Relocation (July 2008 – July 2009):
    Relocate existing utilities along the FRR alignment to lower depths using Horizontal Directional Drilling methods and conventional trenching.
  • Flood Control and Bridge Construction (April 2009 – October 2009):
    Six culverts and two bridges will be constructed during the 2009 dry season. These culverts are either a channel or tunnel that direct water underneath the railroad track. A larger, enhanced culvert will be installed at Berryessa Creek.
  • Track Roadbed and General Construction Activities (October 2008 – October 2010):
    VTA and its contractors will begin to construct newly relocated trackbed next to the current railroad track. This work will involve the importation of a large quantity of soil and granite ballast (trackbed). Simultaneously, work crews will begin to seismically retrofit Able Street Bridge
  • Track Installation and Signal Work (July 2009 – July 2011):
    Upon completion of the tracked installation, UPRR will install new railroad track and signal work to support freight operations along the corridor.
  • Warren Avenue Grade Separation (July 2010 – December 2011):
    Warren Avenue will eventually be grade separated and depressed under and newly constructed single railroad bridge. This work will occur in multiple phases to allow for the continued operation of the railroad.
  • Railroad Abandonment (Summer 2011):
    After all railroad operations are proceeding as normal, the old railroad will be officially abandoned and removed to clear the corridor for future transit.

 Depicts eight mile long railroad corridor, bordered by Interstate 880 to the west and Interstate 680 to the east. The project begins in Fremont and extends south through Milpitas to Monague Boulevard. There are four highlighted areas with photos: Warren Avenue in Fremont, Kato Road in Fremont, Dixon Landing Road in Milpitas and Abel Street Bridge in Milpitas.

How to contact us?

If you have any question concerning the Freight Railroad Relocation Project, please call VTA's Community Outreach Hotline at (408) 321-7575, hearing-impaired (TDD only) (408) 321-2330 or email us at community.outreach@vta.org